K2RQ: Upgrade work on bridges


NEW deck beams will be installed at Padstow’s Memorial Drive Bridge from December 18-19, as part of the Kingsgrove to Revesby Quadruplication project.

The bridge is expected to reopen in March. In the meantime, construction on the bridge deck of Doyle Road Bridge is well under way, with the new bridge expected to be operating by Christmas.

The demolition of the old bridge is scheduled for the weekend of January 15-16. Works to lengthen Davies Road Bridge is also under way.

Source: whereilive